0

Group Of Companies Doctrine Can Be Applied To Bind Non Signatory To An Arbitration Agreement

In a recent judgment in Oil and Natural Gas Corporation Ltd. Versus M/s Discovery Enterprises Pvt. Ltd. & Anr. decided on 27.04.2022 by a three Judges Bench of the Hon’ble Supreme Court, once again the dispute regarding the applicability of the ‘group of companies’ doctrine has been discussed and decided by the Court. The issue arise out of the interim order allowing the application to delete the group entity Jindal Drilling and Industries Limited (JDIL) from the array of parties. A contract for operating a floating, production, storage and offloading vessel was awarded by ONGC to Discovery Enterprises Private Limited (DEPL), a company belonging to the D P Jindal Group. As per the contract, a vessel was to be imported. The vessel was accordingly imported and ONGC paid the customs duty on the understanding that the vessel would be re-exported after completion of work under duty drawback and DEPL shall complete the necessary formalities in this regard. The vessel left Indian territorial waters and did not return. According to ONGC, DEPL failed to complete the formalities for duty drawback and did not compensate ONGC for customs duty and other expenses (Disputed Amount).

Arbitration was invoked by ONGC wherein DEPL and JDIL were made respondent parties. An application under Section 16 of the Arbitration and Conciliation Act, 1996 was filed by JDIL seeking its deletion from the arbitral proceedings on the ground that it is not a party to the arbitration agreement. It was contended by ONGC that DEPL and JDIL belonged to the DP Jindal Group of Companies and since they constitute a single economic entity and the corporate veil should be lifted to compel the non-signatory, JDIL, to arbitrate. The contention of ONGC was based on the fact that JDIL has a vital business interest in DEPL, JDIL is the ultimate beneficiary of the business of DEPL, DEPL has close corporate unity with Jindal Group and the shareholders are almost common, DEPL has throughout represented that they are group company of Jindal amongst the fact that the letter head also depicted the same and that there existed a corporate and functional unity between them.

The Arbitral Tribunal passed an interim award and held that JDIL was not a party to the arbitration agreement and hence the Arbitral Tribunal lacked the jurisdiction to arbitrate on the claims against it. The name of JDIL was therefore deleted from the array of parties.  The Arbitral Tribunal relied on the judgment of Hon’ble Supreme Court in Indowind Energy Ltd. v. Wescare (I) Ltd. & Anr. [(2010) 5 SCC 306]. For the same reason that the Tribunal does not have the jurisdiction, an application filed by ONGC for discovery and inspection was also not allowed. The appeal against the interim award was dismissed by the Hon’ble Bombay High Court on the ground that ONGC failed to show that the companies had common shareholders and common board of directors. Even if this was the case, they do not become the single entity in the light of the judgment in Indowind Energy even if the son and daughter-in-law of the managing director of JDIL are directors in DEPL. The fact remained that JDIL was not the signatory to the contract.

The judgment was challenged under Article 136 of the Constitution.

In the mean while the final award was also delivered allowing the claims of ONGC. ONGC in turn withheld payment due to JDIL in another dispute arising out of 4 agreements between ONGC and JDIL as an adjustment against the dues owed to ONGC by DEPL in the first arbitration. The dispute culminated in an arbitral award in favour of JDIL. This award was challenged under section 34 which was dismissed. The appeal against the order was also dismissed and finally the jurisdiction of the Hon’ble Supreme Court under Article 136 was invoked. This case, on the request of ONGC, was transfered before the Bench looking into the validity of the interim award passed in the first arbitration deleting JDIL from the array of parties.

The Hon’ble Supreme Court started its analysis by looking into the definition of arbitration agreement provided under section 7 of the Arbitration and Conciliation Act, 1996.  Further, expression “party” is defined in Section 2(h) to mean a party to an arbitration agreement. The Court observed that the judgment in Indowind Energy deals with interpretation of the term “parties” vis-à-vis an arbitration agreement in the context of an application for the appointment of an arbitrator under Section 11(6) of the 1996 Act. The Court in the matter had concluded that Indowind in no communication had ever acknowledged or confirmed that it was a party to the arbitration agreement. It was held that “Each company is a separate and distinct legal entity and the mere fact that the two Companies have common shareholders or common Board of Directors, will not make the two Companies a single entity. Nor will the existence of common shareholders or Directors lead to an inference that one company will be bound by the acts of the other.” It was further observed that “The very fact that the parties carefully avoided making Indowind a party and the fact that the Director of Subuthi though a Director of Indowind, was careful not to sign the agreement as on behalf of Indowind, shows that the parties did not intend that Indowind should be a party to the agreement.”

The Court also analysed the judgments in Chloro Controls India Pvt. Ltd. v. Severn Trent Water Purification Inc. & Ors (2013) 1 SCC 641, Cheran Properties Ltd. v. Kasturi & Sons Ltd. & Ors (2018) 16 SCC 413 and MTNL v. Canara Bank & Ors. 16 (2020) 12 SCC 767. In Chloro Controls India it was held that “an arbitration agreement entered into by a company, being one within a group of companies, can bind its non-signatory affiliates or sister or parent concerns, if the circumstances demonstrate that the mutual intention of all the parties was to bind both the signatories and the non-signatory affiliates”. It was further held that in exceptional cases “a non-signatory party could be subjected to arbitration provided these transactions were with group of companies and there was a clear intention of the parties to bind both, the signatory as well as the non-signatory parties. In other words, “intention of the parties” is a very significant feature which must be established before the scope of arbitration can be said to include the signatory as well as the non-signatory parties.” Direct relationship to the party signatory to the arbitration agreement; direct commonality of the subject matter; and whether the agreement is of a composite transaction where the performance of a mother agreement may not be feasible without the execution or performance of a subsidiary or ancillary agreement were stated to be relevant questions to be applied in the facts and circumstances of the case while determining the applicability o fthe doctrine of group companies.

The principle was subsequently applied to Ameet Lalchand Shah & Ors. v. Rishabh Enterprises & Anr (2018) 15 SCC 678 where in it was held that “a non-signatory would be bound by the arbitration clause in the mother agreement, since it is a party to an inter-connected agreement, executed to achieve a common commercial goal.” In Cheran Properties group of companies doctrine was applied against a non-signatory to the arbitration agreement in the case of the enforcement of a domestic arbitration award. It was held that “the group of companies doctrine has been applied to pierce the corporate veil to locate the “true” party in interest, and more significantly, to target the creditworthy member of a group of companies.” A word of caution was however added that since the doctrine stares at the face of established principle companies being separate legal entity, the doctrine may be applied after construction of the arbitration agreement and analysis of the circumstances relating to the entry into and performance of the underlying contract. So where there is a conscious intention of the parties to subject themselves to separate arbitration agreements under their individual contracts, the doctrine shall not apply (Duro Felguera v. Gangavaram Port Limited (2017) 9 SCC 729). Similarly, a mere existence of an indemnity by the foreign company, in the absence of any other factors, would not signify its intention to be bound by the arbitration agreement (Reckitt Benckiser (India) P Ltd. v. Reynders Label Printing (2019) 7 SCC 62). In MTNL the Hon’ble Court had on the same lines observed that the doctrine is applicable where conduct of the parties evidences that there is clear intention of the parties to bind a non-signatory. The Courts generally satisfy themselves that non-signatory company was a necessary party to the contract. The instances of conduct may be when non-signatory entity on the group has been engaged in the negotiation or performance of the commercial contract, or made statements indicating its intention to be bound by the contract, the non-signatory will also be bound and benefitted by the relevant contracts.

The Court appreciated the work of Gary B. Born, according to whom a group of companies doctrine has also been invoked in cases where there is a tight group structure with strong organisational and financial links, so as to constitute a single economic unit, or a single economic reality or when that party is an ‘alter ego’ of an entity which is signatory.  As per John Fellas, the principle of binding a non-signatory can also be looked from the angle of the doctrine of estoppel where the non-signatory group entity which has been reaping the benefits of the contract shall be directly estopped from taking inconsistent position and disavowing the obligations under the contract.

On analysing various judgments and views of the scholars, the Court propounded that the factors of mutual intent of the parties, relationship of a non-signatory to a party which is a signatory, commonality of the subject matter, composite nature of the transaction and performance of the contract shall determine whether a company within a group of companies which is not a signatory to arbitration agreement would be bound by the arbitration agreement.

On facts, the Court observed that the Arbitral Tribunal erred in not deciding the application for inspection and discovery and deferring it instead despite the fact that inspection and discovery was relevant for the determination of applicability of doctrine of group companies. In addition to the submissions of ONGC before the Tribunal, it was also stated in the course of the evidence by ONGC’s witness that almost all the senior officers of JDIL, including its Managing Director, actively participated in matters relating to the hiring of the vessel, its deployment, performance and related issues. ONGC’s assertions were based on the fact that even in the initial meeting between ONGC and DEPL, General Manager of JDIL attended on behalf of the DEPL. The Court regretted to state that the Ld. Tribunal did not even consider whether the group of companies doctrine would be applicable and precluded itself from deciding as to whether the application for discovery and inspection should be allowed which in turn “goes to the root of the process in as much as it disabled ONGC from pursuing its fundamental claim based on the application of the group of companies doctrine.”  The Court further observed that if the Arbitral Tribunal accepts a plea that it lacks jurisdiction, the order of the Tribunal is amenable to a challenge in appeal under Section 37(2)(a) and therefore it cannot be conclusive as it is subject to an appellate remedy.

While applying the law to the two appeals arising out of two different transactions, the Court observed that the issue of jurisdiction arose only in the first set of proceedings between ONGC, DPEL and JDIL. DEPL was not a party to the second proceeding. However, the evidence in one proceedings was used in the subsequent proceedings. In the subsequent proceeding between ONGC and JDIL, ONGC did not plead any defence on merits but asserted a right to adjust the amounts which were due to JDIL against the claims which ONGC had against DEPL under a distinct contract which was in dispute in the first proceeding. In this light the Court observed that there was significant amount of overlapping in the two arbitrations which was further confirmed by the fact that the grounds on which ONGC opposed JDIL’s application under Section 16 in the first arbitral proceeding overlapped with the basis on which ONGC sought adjustment of the claims due to JDIL in the second arbitral proceeding and Arbitral Award in the second proceeding relied on the findings contained in the interim award of the first Arbitral Tribunal.

The Court further took note of the deposition of the ONGC’s witness. It was deposed that first meeting was attended by the General Manager of JDIL, the expression of interest was signed by Manager (Commercial and Development), JDIL, bid was submitted by DEPL with a resume that stated it to be the part of the DP Jindal Group of Companies, DEPL and JDIL shared a common addresses and telephone numbers, DEPL was created by the Jindal Group with the definite purpose of rendering a particular service to the oil and gas sector, DEPL has indicated on the website that it works under the “fraternal hood of the said group, DEPL is promoted and managed by the son and daughter in law of the Managing Director of JDIL, bid was submitted by employee of JDIL, the Managing Director of JDIL had negotiated with the owners of the vessel for hiring on behalf DEPL etc. The Court found the deposition relevant and stated that there was merit in the submission which was been urged on behalf of the ONGC that the application for discovery and inspection had to be decided before the plea of jurisdiction was adjudicated upon. The Court went on to observe that the primary basis for the determination by the Tribunal of an absence of jurisdiction was that the arbitration agreement was between ONGC and DEPL whereas the legal foundation of the group of companies doctrine was not evaluated, on facts or law.

The Court accordingly held that “the first Arbitral Tribunal has made a fundamental error of law in not deciding the application by ONGC on discovery and inspection of documents before it ruled on jurisdiction. In doing so, the first Arbitral Tribunal’s interim award dated 27 October 2010 goes against the principles of natural justice. The failure to consider the application for discovery and inspection of documents results in a situation where vital evidence that could have assisted the Tribunal in its determination of the challenge under Section 16 was shut out. As a matter of fact, it emerged from the record that no evidence was adduced by JDIL in support of its plea of the absence of jurisdiction under Section 16. JDIL having taken the plea of absence of jurisdiction was required to establish the grounds on which it set about to establish its plea.”

0

Does non-compliance of Section 29A of Arbitration and Conciliation Act, 1996 vitiates the Arbitral Award?

Section 29A of the Arbitration and Conciliation Act, 1996 prescribes the time limit for passing of arbitral award in case of domestic arbitrations. As per section 29A(1), the award shall be made by the arbitral tribunal within a period of 12 months from the date of completion of pleadings. As per sub-section (3), the parties by consent extend the period of 12 months for a further period not exceeding 6 months. As per sub-clause (4), the mandate of the arbitrator shall terminate in the event the award is not made within the period prescribed or within the extended period unless the court extends the period either prior to or after the expiry of the period so specified or extended. Any extension can be granted only on application of any of the parties stating sufficient cause. The Court may impose any terms and conditions while extending the time period. The Court deciding an application under section 29A of the 1996 Act is also empowered to order reduction in the fees of the arbitral tribunal if the Court is of the opinion that the delay in delivering award is attributable to the arbitral tribunal. The Court can further impose actual or exemplary costs upon any of the parties.

The question that arises for consideration is whether an award that is passed after the expiry of the period prescribed under section 29A of the 1996 Act or after the extended period, is a nullity and is unenforceable in law? The question is also whether section 29A addresses the said issue at all or it is a grey area? It is also important to understand as to under which proceeding the objection of award being nullity can be raised.

Hon’ble Division Bench of the Telangana High Court has recently in the matter of Roop Singh Bhatty v. M/s. Shriram City Union Finance Limited C.R.P.NO.1354 OF 2021 [decide on 08.04.2022] held that the award passed by the arbitral tribunal after one year of entering into reference is nullity and void ab initio since after one year so prescribed under Section 29A as it then existed, the arbitral tribunal became functus officio and is wholly incompetent to deal with the disputes or pass the arbitral award. Thus, in law there does not exist an arbitral award and therefore there is no question of enforcement of the award.

In the matter of Roop Singh Bhatty the dispute arose out of the default in repayment of loan by the petitioner to the respondent subsequent to which the Respondent invoked the arbitration clause. The arbitrator passed the award on 27.12.2017 in favour of the respondent. The respondent filed a petition in the Court seeking execution of the arbitral award which was allowed in favour of the Respondent. The Petitioner preferred a revision against the said execution order. The fulcrum of challenge was that award was not passed within one year from the date of filing claim, and therefore the award is a nullity and therefore cannot be enforced. When asked if such plea can be taken at the execution stage, it was submitted that plea of nullity can be raised in execution proceedings and not at the Section 34 proceeding as the scope of challenge to the award under Section 34 is limited. The Counsel for the respondent on the other hand argued that Section 29A of the 1996 Act only lays down procedure and non-compliance thereof does not vitiate the award.

The Hon’ble High Court began its analysis by looking into the relevant provision under section 29A and its scope as it stood at the time of adjudication of the disputes between the parties. As of then, Section 29A provided that the award should be passed within a period of twelve months from the date Arbitration Tribunal enters appearance. The relevant provision is reproduced herein below:

Section 29A. (1) The award shall be made within a period of twelve months from the date the arbitral tribunal enters upon the reference. Explanation:- For the purpose of this sub-section, an arbitral tribunal shall be deemed to have entered upon the reference on the date on which the arbitrator or all the arbitrators, as the case may be, have received notice, in writing, of their appointment.

(2) If the award is made within a period of six months from the date the arbitral tribunal enters upon the reference, the arbitral tribunal shall be entitled to receive such amount of additional fees as the parties may agree.

(3) The parties may, by consent, extend the period specified in sub-section (1) for making award for a further period not exceeding six months.

(4) If the award is not made within the period specified in sub-section (1) or the extended period specified under subsection (3), the mandate of the arbitrator(s) shall terminate unless the Court has, either prior to or after the expiry of the period so specified, extended the period: Provided that while extending the period under this sub-section, if the Court finds that the proceedings have been delayed for the reasons attributable to the arbitral tribunal, it may order reduction of fees of arbitrator(s) by not exceeding five per cent for each month of such delay.

(5) The extension of period referred to in sub-section (4) may be on the application of any of the parties and may be granted only for sufficient cause and on such terms and conditions as may be imposed by the Court.

(6) While extending the period referred to in sub-section (4), it shall be open to the Court to substitute one or all of the arbitrators and if one or all of the arbitrators are substituted, the arbitral proceedings shall continue from the stage already reached and on the basis of the evidence and material already on record, and the arbitrator(s) appointed under this section shall be deemed to have received the said evidence and material.

(7) In the event of arbitrator(s) being appointed under this section, the arbitral tribunal thus reconstituted shall be deemed to be in continuation of the previously appointed arbitral tribunal.

(8) It shall be open to the Court to impose actual or exemplary costs upon any of the parties under this section.

(9) An application filed under sub-section (5) shall be disposed of by the Court as expeditiously as possible and endeavour shall be made to dispose of the matter within a period of sixty days from the date of service of notice on the opposite party.

The arbitral tribunal is deemed to have entered the appearance when he receives the notice for its appointment from the parties. The date on which the arbitral tribunal entered the appearance was not disputed between the parties. The award, however, was not made within 1 year from that date. As per the Court, the provision under section 29A is in mandatory terms. The Court observed that “The provision as it stood was in mandatory terms and leaves no scope to infer otherwise. The intention of the Parliament is made abundantly clear from the reading of Sub-sections (3) and (4). Subsection (3) enables parties by consent to extend the time by further period of six months. But it also makes it clear that it should not be extended beyond six months. According to sub-section (4), after the initial period of one year and extended period of six months, if extended by consent, the mandate of the arbitrator terminates. Thus, he becomes functus-officio after that period and, therefore, seizes to be an arbitrator. An arbitrator is a creature of the statute and has to work within the four corners of the Act.”

This provision was subsequently amended vide Arbitration and Conciliation (Amendment) Act, 2019. As per section 6 of the Amendment Act of 2019 – “In Section 29A of the principal Act,- (a) for sub-section (1), the following sub-section shall be substituted, namely:-“(1) The award in matters other than international commercial arbitration shall be made by the arbitral tribunal within a period of twelve months from the date of completion of pleadings under sub-section (4) of Section 23: Provided that the award in the matter of international commercial arbitration may be made as expeditiously as possible and endeavour may be made to dispose of the matter within a period of twelve months from the date of completion of pleadings under sub-Section (4) of Section 23.”; (b) in sub-section (4), after the proviso, the following provisos shall be inserted, namely:- “Provided further that where an application under sub-section (5) is pending, the mandate of the arbitrator shall continue till the disposal of the said application: Provided also that the arbitrator shall be given an opportunity of being heard before the fees is reduced”.”

As per the counsel of the respondent, the operation of amendment was retrospective in nature. The argument was rejected by the Court. Although the amendment takes care of the drawbacks in the earlier provision, the Court explained that “merely because word substitution is used [in section 6 of the Arbitration and Conciliation (Amendment) Act, 2019], the amended provision does not relate back to the date of original provision that was amended. It depends on the language employed, effect of the amendment and the intendment of the legislature.” The position is rather made clear by the notification which appointed the effective date for the amendments under 2019 Amendment Act as 30th August, 2019.

The Court therefore finally concluded that the execution Court grossly erred in not appreciating the fact that the arbitral tribunal passed the award after one year of appearance when it became functus officio and wholly incompetent to deal with the disputes or pass the arbitral award. Thus, award passed by the arbitrator was nullity and void ab initio. Thus, in law there did not exist any arbitral award and there was no question of enforcement of the award.

The provision under section 29A of the 1996 Act or any other provision does not provide a clear answer to the question raised in the present case. It is however stated that the mandate of the arbitrator shall terminate after the expiry of the term provided under section 29A(1) or 29A(3) of the 1996 Act, as the case may be.  The position remains unchanged so far as the two amendments of 2015 and 2019 in the 1996 Act are concerned and therefore the reasoning given by the Hon’ble Telangana High Court shall be equally applicable to the disputes being adjudicated by the arbitral tribunals after the amendment to section 29A of 1996 Act in 2019.

0

Sufficiency Of Stamp Duty On Agreement Cannot Be Adjudicated By Court at Pre-<br>reference Stage Under Section 11 Of Arbitration and Conciliation Act, 1996

In the matter of Parsvnath Developers Ltd v. Future Retail Limited (ARB.P. 14/2020) before Hon’ble Delhi High Court [decided on 12.04.2022], the petitioner moved an application under section 11(6) of the Arbitration and Conciliation Act, 1996 (“1996 Act”) for appointment of the presiding arbitrator in a dispute that erupted between the parties in relation to the Sub-License Agreement. Under the said agreement, the petitioner had sub-licensed certain area of the Parsvnath Mall to the Respondent for running a departmental store under the name of ‘Big Bazaar’.

The dispute arose on account of the introduction of service tax on the service of renting/licensing of immovable properties for commercial use with effect from 01.06.2007 under the Finance Act, 2007 enacted by the Government of India.  As per the Petitioner, the Respondent was liable to bear the additional burden of service tax. However, the Respondent failed to reimburse the service tax paid by the Petitioner. It was contended by the Respondent that it was liable to pay any service tax since there was no stipulation contained in the Sub-License Agreement for payment of service tax. Between the period of period 01.06.2007 to 31.12.2017, the amount payable added up to Rs. 4,27,93,994/- towards service tax and GST.

When the parties approached the Hon’ble High Court, the moot question for determination was since the main Agreement is not sufficiently stamped whether the petition for appointment of an arbitrator is required to be rejected?

The Hon’ble Court referred to the judgments in N.N. Global Mercantile Pvt. Ltd. v. Indo Unique Flame Limited & Ors (2021) 4 SCC 379 and Garware Wall Ropes Limited v. Coastal Marine Constructions & Engineering Limited (2019) 9 SCC 209 wherein the Hon’ble Supreme Court held that non-payment or deficiency of stamp duty did not invalidate the main contract.  By virtue of doctrine of severability, the arbitration agreement or arbitration clause in a main contract is an independent agreement. It does not require mandatory registration. Therefore, invalidation of main contract on account of non-stamping, insufficient stamping or non-registration does not necessarily affect the arbitration agreement adversely.

The Court also referred to the law laid down in the matter of Vidya Drolia and Ors. v. Durga Trading Corporation (2021) 2 SCC 1 wherein a thumb rule of non-interference was laid down by the Hon’ble Supreme Court at the stage of reference unless it is found that the disputes ex facie are not arbitrable or the principal agreement is plainly invalid and unenforceable. It was held that the Courts would abstain from carrying out any adjudicatory exercise in respect of any contentious issue at a pre-reference stage.

The Court went on to further affirm the settled position by virtue of Section 6A of the  Arbitration and Conciliation Act, 1996 which lays down plainly that the scope of examination under Section 11 of the Arbitration and Conciliation Act, 1996 is confined to the existence of an Arbitration Agreement. The Court in this regard referred to the judgment in Duro Felguera, S.A. v. Gangavaram Port Limited (2017) 9 SCC 729. The Court also went on to analyse Mayavati Trading Pvt. Ltd. v. Pradyuat Deb Burman (2019) 8 SCC 714 and Bharat Sanchar Nigam Limited and Ors. v.Nortel Networks India Pvt. Ltd. (2021) 5 SCC 738.It was held in the matter of Bharat Sanchar Nigam Limited  thatIt is only in the very limited category of cases, where there is not even a vestige of doubt that the claim is ex facie time-barred, or that the dispute is non-arbitrable, that the court may decline to make the reference. However, if there is even the slightest doubt, the rule is to refer the disputes to arbitration, otherwise it would encroach upon what is essentially a matter to be determined by the tribunal.” Similarly in the matter of NCC Limited v. Indian Oil Corporation Limited (2019) SCC OnLine Del 6964, it was held that “Thus, unless it is in a manner of speech, a chalk and cheese situation or a black and white situation without shades of grey, the concerned Court hearing Section 11 petition should follow the more conservative course of allowing parties to have their say before the Arbitral Tribunal”.

The Court therefore concluded that although there was an existing dispute as to whether the contract was sufficiently stamped or not and the same was contentious issue in the light of the arguments forwarded by the petitioner that Agreement was in the nature of leave and license and did not create any interest in respect of the premises in question, in favour of the respondent. In the light of same position of law, the Court further stated that the question of limitation, which is a mixed question of law and facts, is also required to be examined, not at the pre-reference stage by the Court but subsequently by the Arbitral Tribunal. The Court referred to the judgment in Uttarakhand Purv Sainik Kalyan Nigam Ltd. v. Northern Coal Field Ltd (2020) 2 SCC 455. In the said judgment the Hon’ble Apex Court made the following observation:

In view of the provisions of Section 16, and the legislative policy to restrict judicial intervention at the pre-reference stage, the issue of limitation would require to be decided by the arbitrator. Sub-section (1) of Section 16 provides that the Arbitral Tribunal may rule on its own jurisdiction, “including any objections” with respect to the existence or validity of the arbitration agreement. Section 16 is as an inclusive provision, which would comprehend all preliminary issues touching upon the jurisdiction of the Arbitral Tribunal. The issue of limitation is a jurisdictional issue, which would be required to be decided by the arbitrator under Section 16, and not the High Court at the pre-reference stage under Section 11 of the Act. Once the existence of the arbitration agreement is not disputed, all issues, including jurisdictional objections are to be decided by the arbitrator.

In the light of the discussion the Hon’ble Court appointed an arbitrator for the adjudication of the disputes between the parties.

0

Whether pendency of CIRP against the Corporate Debtor is a Condition Precedent for Initiating Insolvency against the Personal Guarantor?

In the matter of State Bank of India, Stressed Asset Management Branch  v. Mahendra Kumar Jajodia Company Appeal (AT) Insolvency No. 60 of 2022, State Bank of India (“Appellant”) approached the Hon’ble National Company Law Appellate Tribunal (“NCLAT”) against the order of Ld. National Company Law Tribunal, Kolkota (“NCLT”). Vide impugned order, NCLT, Kolkata had rejected the application of the Appellant under Section 95(1) of the Insolvency and Bankruptcy Code, 2016 (“IBC”) seeking initiation of Corporate Insolvency Resolution Process against the Guarantor. As per the NCLT, the application was premature as on date of application there was no Corporate Insolvency Resolution Process (“CIRP”) or Liquidation Process pending against the Corporate Debtor because of approval of the Resolution Plan. Since Section 60(2) of the Code prerequisites that there must be CIRP or Liquidation Process pending against the principal borrower or the corporate debtor for initiation of an insolvency resolution process to be initiated against the personal guarantor, the application was liable to be dismissed.

On analysis of Section 60(2) of the IBC, the Hon’ble NCLAT held that purpose and object of Section 60(2) of the IBC is that “when proceedings are pending in ‘a’ National Company Law Tribunal, any proceeding against Corporate Guarantor should also be filed before ‘such’ National Company Law Tribunal. The idea is that both proceedings be entertained by one and the same NCLT. The sub-section 2 of Section 60 does not in any way prohibit filing of proceedings under Section 95 of the Code even if no proceeding are pending before NCLT.” It was further clarified by the Hon’ble NCLAT that Section 60(2) was applicable in a limited circumstances i.e. only when a CIRP or Liquidation Proceeding of a Corporate Debtor is pending before NCLT. In cases where CIRP is not pending against the corporate debtor, section 60(1) shall apply.

The NCLAT explained that the provision of Section 60(2) are without prejudice to Section 60(1) and are supplemental to Section 60(1) which provides that Adjudicating Authority in relation to Insolvency or Liquidation for Corporate Debtor including Corporate Guarantor or Personal Guarantor shall be the NCLT having territorial jurisdiction over the place where the Registered Office of the Corporate Person is located. Therefore, section 60(1) is the substantive provision and can be invoked in the cases which do not fall under section 60(2) of the IBC.

The Hon’ble NCLAT, therefore, allowed initiation of insolvency resolution process against the personal guarantor under section 95(1) of the Code, although no CIRP of the corporate debtor was pending before the NCLT.

It is important to note that the CIRP was initiated against the corporate debtor but has ceased to continue on account of approval of the resolution plan. Interestingly, section 60(2) provides for two situation only i.e. “where a corporate insolvency resolution process or liquidation proceeding of a corporate debtor is pending before a National Company Law Tribunal”.

The order has been now challenged by the personal guarantor before the Hon’ble Supreme Court where the moot question is whether Insolvency Resolution Process can be initiated against the Personal Guarantor in the absence of Corporate Insolvency Resolution Process. This absence of CIRP may arise out of the fact that there is no CIRP initiated against the corporate debtor at all or that it commenced but terminated on account of approval of resolution plan. The situation that the CIRP culminates into commencement of Liquidation Process has been squarely covered by the provision under section 60(2) of the IBC.

The Division Bench of the Hon’ble Supreme Court comprising of Justice Abdul Nazeer and Justice Vikram Nath vide order dated 21.03.2022 stayed the operation of order of the Hon’ble NCLAT and issued notice while citing Paragraph 95 in the judgment of Lalit Kumar Jain v. Union of India 2021(9)SCC321 wherein it was held that:

Section 60(2) prescribes that in the event of an ongoing resolution process or liquidation process against a corporate debtor, an application for resolution process or bankruptcy of the personal guarantor to the corporate debtor shall be filed with the concerned NCLT seized of the resolution process or liquidation. Therefore, the Adjudicating Authority for personal guarantors will be the NCLT, if a parallel resolution process or liquidation process is pending in respect of a corporate debtor for whom the guarantee is given. The same logic prevails, under Section 60(3), when any insolvency or bankruptcy proceeding pending against the personal guarantor in a court or tribunal and a resolution process or liquidation is initiated against the corporate debtor. Thus if A, an individual is the subject of a resolution process before the DRT and he has furnished a personal guarantee for a debt owed by a company B, in the event a resolution process is initiated against B in an NCLT, the provision results in transferring the proceedings going on against A in the DRT to NCLT.”

0

Court can Pass an Order under Contempt of Courts Act, 1971 for Willful Disobedience of an Executable Order/Award of Arbitral Award

The matter pertains to judgment in Urban Infrastructure Real Estate Fund v. Dharmesh S. Jain and Anr. [Contempt Petition (C) No. 940 of 2021] passed by the Hon’ble Supreme Court on 10.03.2022. The Petitioner initiated arbitral proceedings and received an Arbitral Award dated 30.08.2018 in its favour. The Arbitral Tribunal directed the respondent for specific performance of the Share Purchase Agreement and also directed recovery of an amount of Rs. 78,33,37,500/- along with the interest from the respondents. The Arbitral Award was challenged under section 34 of the Arbitration and Conciliation Act, 1996. The Award Debtor further moved a notice of motion praying for the stay of the Award. The Hon’ble Single Bench of the Delhi High Court granted the interim stay on the condition that respondents deposit 50% of the awarded sum within twelve weeks.

The order of the Hon’ble Single Bench was challenged by the respondents. The application was dismissed by the Division Bench of the Hon’ble High Court. The respondents then preferred a special leave petition which was also dismissed by the Hon’ble Supreme Court vide order dated 28.10.2021. The Court, however, granted the respondents a period of eight weeks, as prayed, for depositing 50% amount as directed by the Single Bench with a rider that non-compliance of the order shall be taken very seriously and non-deposit of the amount shall be considered to be non-compliance of the order of the Hon’ble Supreme Court with serious consequences.

The respondents not only miserably failed to comply with the orders of the Hon’ble Supreme Court despite various reminders and a legal notice issued by the Petitioner, but also moved an application before the Hon’ble Supreme Court praying for recall of order dated 28.10.2021. The application was dismissed by a detailed order dated 25.01.2022.

The Petitioner moved an application alleging disobedience of the order dated 28.10.2021. The application was opposed by the respondents inter alia on the ground that section 36 of the Arbitration and Conciliation Act, 1996 separately provides for execution of award and “the weapon of contempt cannot be used for purposes of executing a decree or implementing an order for which law provides appropriate procedure” [reliance placed on R.N. Dey and Ors. Vs. Bhagyabati Pramanik and Ors., (2000) 4 SCC 400]. Petitioners on the other hand pleaded that as on date the total amount due from the respondents was Rs. 190 crore. The respondents, on one pretext or the other, have been taking extensions of time for deposit of the 50% amount as directed.

As to the findings of fact, the Hon’ble Supreme Court observed that for approximately two years, the respondents have been able to successfully avoid deposit of the 50% amount by seeking extensions and consequently has obstructed the execution proceedings for this long. The order directing the respondents to disclose their assets was not complied until 2 years. The Court rejected the argument of the respondent that since they have not deposited the amount as per the order dated 08.08.2019, necessary consequences under Section 36 of the 1996 Act shall follow and the execution proceedings have to be proceeded further. The Court opined that the conduct of respondent was an abuse of process of law. It showed the wilful disobedience of the respondent by non-compliance of the order that included order of the Hon’ble High Court as well as the Hon’ble Supreme Court, more so when the application for recall of its order dated 28.10.2021 was dismissed by the Hon’ble Supreme Court. This also belied the contention of the respondent that order dated 28.10.2021 was not a mandatory order when the respondent itself applied for its recall. The respondent had gone ahead to consciously not comply with order dated 28.10.2021 even when it was specifically observed in the order that non-compliance of the said order shall be treated very seriously and non-deposit of the amount as directed by the High Court shall be treated as non-compliance of the order of this Court and also having a serious consequence.

With regard to the case laws cited by the respondents, the Court observed that “We are mindful of the fact that contempt proceedings should not be of the nature of ‘execution proceedings in disguise.’ However, we hold that the case law cited supra would not come to the aid of the contemnor herein as the facts of the said case were significantly different from the case at hand. In the said case, no stay was operating on the decree of which contempt was alleged. Therefore, the decree-holder therein could very well initiate execution proceedings.” In the present case, the award was stayed subject to the deposit of an amount.

While dealing with the argument of the respondent that failure to comply with the order dated 28.10.2021 would have no consequences under the Contempt of Courts Act, 1971, the Court observed that “it is trite law that the jurisdiction of a Court under the Act, would not cease, merely because the order or decree of which contempt is alleged, is executable under law, even without having recourse to contempt proceedings.” The Court clarified that “Contempt jurisdiction could be invoked in every case where the conduct of a contemnor is such as would interfere with the due course of justice”. The Court further elaborated that “Contempt is a matter which is between the Court passing the order of which contempt is alleged and the contemnor; questions as to executability of such order is a question which concerns the parties inter-se. The power of the Court to invoke contempt jurisdiction, is not, in any way, altered by the rights of the parties inter-se”. The reliance was placed on Bank of Baroda vs. Sadruddin Hasan Daya  [(2004) 1 SCC 360] and Rama Narang vs. Ramesh Narang  [(2006) 11 SCC 114.

The Court explained that when an order or direction is given by the Court, the party is required to comply with the order within the time given and if the party is unable to do the needful in the given time, the party is required to apprise the Court of the same to seek reasonable extension of time. If the party has not resorted to either of the two things and has caused delay in compliance, the said party is liable for contempt. The further relied on Maruti Udyog vs. Mahinder C. Mehta AIR 2008 SC 309 where in it was held that the conduct of the contemnor is the relevant factor in determining the offence of contempt and this is irrespective of whether the decree is executable or not.

On the basis of the above discussion, the Court held that the conduct of the respondent-contemnors justified invocation of contempt jurisdiction of this Court.

D & H India Ltd. vs Superon Schweisstechnik India Ltd. [FAO(OS)(COMM) No. 237/2019] decided on 16.03.2020 it was held that On a plain reading, the proviso to Section 13 (1A) of the Commercial Courts Act is an enabling, rather than a disabling, provision. There is nothing, in the said proviso, which would seem to indicate that it dilutes the effect of sub-section (1A) of Section 13. If we were to read the said proviso as excluding, from the jurisdiction of the appellate court, all orders, passed by a Commercial Court, save and except those which find specific enumeration in Order XLIII of the CPC, it may amount to rewriting the proviso to read “Provided that no appeal shall lie, except from such orders passed by a Commercial Division or the Commercial Court as are specifically enumerated under Order XLIII of the Code of Civil Procedure, 1908 (5 of 1908) as amended by this Act and section 37 of the Arbitration and Conciliation Act, 1996 (26 of 1996).” We are not convinced that the province of our jurisdiction, in the present case, allows us to so legislate. To our mind, therefore, sub-section (1A) of Section 13 of the Commercial Courts Act allows appeals to be preferred against all judgements and orders of the Commercial Division of the High Court, to the Commercial Appellate Division thereof, and the proviso, to the said sub-section merely clarifies that, in the case of orders specifically enumerated in Order XLIII of the CPC, such appeals shall lie Order XLI Rule 1(3) and Rule 5 also provide for opportunity to the judgment debtor to obtain a stay against the decree upon deposit of the disputed amount in the Court.

1 5 6 7 8 9

You cannot copy content of this page

Left Menu Icon

DISCLAIMER & CONFIRMATION

The Bar Council of India does not permit advertisement or solicitation by advocates in any form or manner.

By clicking “Proceed” button below and accessing this website (www.nautiliyaalegal.com), the user fully accepts that he/she is seeking information of his/her own accord and volition and that no form of solicitation has taken place by the firm or its members.

The information provided under this website is solely available at your request for information purposes only. It should not be interpreted as soliciting or advertisement. The firm is not liable for any consequence of any action taken by the user relying on material / information provided under this website. In cases where the user has any legal issues, he/she in all cases must seek independent legal advice.