0

Whether The Applicant Can Be Permitted To Adduce Evidence To Support The Ground Relating To Public Policy In An Application Filed Under Section 34 Of The Arbitration & Conciliation Act, 1996

In a recent  matter between M/s Alpine Housing Development Corporation Pvt. Ltd. (“Appellant”) and  Ashok S. Dhariwal and Others (“Respondents”) [CIVIL APPEAL NO. 73 OF 2023], the Appellant  approached  Hon’ble Supreme Court against the order by the High Court of Karnataka in a Writ Petition, by which the High Court had set aside the order passed by the learned Additional City Civil and Sessions Judge, and permitted the Respondents to adduce evidence in an interim application under Section 34 of the Arbitration & Conciliation Act, 1996 (“Act”). The award, passed in 1998, was an ex-parte arbitral award wherein no evidence was led by the Respondents.

The interim application filed along with the application under Section 34 of the Act by the Respondents, was rejected by the learned Additional City Civil and Sessions Judge refusing to permit the Respondents to adduce evidence on the ground that it would delay further hearing of section 34 application. The Court relied on Section 34(2)(a) of the Act, as amended in the year 2019, by which expression “furnish proof” in section 34(2)(a) came to be substituted with the expression “establish on the basis of record of arbitral tribunal”.

The Hon’ble High Court while following the decision of Supreme Court in the case of Fiza Developers and Inter-Trade Private Limited v. AMCI (India) Private Limited & Another [(2009) 17 SCC 796] allowed the writ petition filed by the Respondents and set aside the order passed by the lower court permitting them to adduce evidence in the proceedings under section 34 of the Act. The Court reasoned that the provisions of Section 34 (2)(a) of the Act, as it stood prior to the amendment in 2019, would apply.

The Appellant approached the Hon’ble Supreme Court.

The Supreme Court, at the very outset, laid down that since the arbitration proceedings commenced and even the award was declared prior to the amendment of Section 34(2)(a) in 2019, therefore, Section 34(2)(a) pre-amendment shall be applicable. The Court further reasoned that there was a substantial change vide amendment of section 34(2)(a) by 2019 amendment. Prior to the amendment of section 34(2)(a), an arbitral award could be set aside by the Court if the party making an application “furnishes proof” and the grounds set out in section 34(2)(a) and section 34(2)(b) are satisfied. However, subsequent to the amendment of section 34(2)(a), the words “furnishes proof” have been substituted by the words “establishes on the basis of the record of the arbitral tribunal”. The Court, therefore opined that in case of arbitration proceedings commenced and concluded prior to the amendment of section 34(2)(a) by Act 33/2019, pre-amendment of section 34(2)(a) shall be applicable.

The Court, after examining the findings in the judgments of  Fiza Developers, Canara Nidhi Limited v. M. Shashikala [(2019) 9 SCC 462] and Emkay Global Financial Services Limited v. Girdhar Sondhi [(2018) 9 SCC 49], concluded that the three judgments lay down the position and the scope and ambit of section 34(2)(a) pre-amendment. Section 34 application will not ordinarily require anything beyond the record that was before the arbitration and that cross-examination of persons swearing in to the affidavits should not be allowed unless absolutely necessary. The Court made the observation saying that the ratio of the aforesaid three decisions on the scope and ambit of section 34(2)(a) pre-amendment would be that applications under sections 34 of the Act are summary proceedings. An award can be set aside only on the grounds set out in section 34(2)(a) and section 34(2)(b). Speedy resolution of the arbitral disputes is the objective behind the legislation. Therefore in the proceedings under section 34 of the Arbitration Act, the issues are not required to be framed which would otherwise defeat the said object of speedy resolution.

So far as leading evidence is concerned the Court observed that ordinarily in the Section 34 proceedings, the examination by the Court shall not require anything beyond the record that was before the arbitrator. However, the Court added, if there are matters not contained in such records and the relevant determination to the issues arising under section 34(2)(a), they may be brought to the notice of the Court by way of affidavits filed by both the parties in exceptional cases, although cross-examination of the persons swearing in to the affidavits should not be allowed unless absolutely necessary.  The Court further added that the requirement of “furnishing proof” as per pre-amendment of section 34(2) (a) of the Arbitration Act shall also be equally applicable to the application for setting aside the award on the grounds set out in section 34(2)(b) such as the ground of public policy, provided the same cannot be established and proved from the record before the arbitrator.

After setting the law, the Court went on to examine whether the Respondents were able to establish  an exceptional case that it is necessary to grant opportunity to the Respondents to file affidavits and adduce evidence. Factually, the Court found that the evidence sought to be brought on record vide the interim application was subsequent to the passing of the award and therefore naturally the same shall not be forming part of the record of the arbitral tribunal. Additionally, the award of the arbitral tribunal was an ex-parte award and no evidence was before the arbitral tribunal on behalf of the Respondents. The affidavit, on the other hand, discloses specific document and the evidence required to be produced in order to determine the issue at hand. In that view of the matter, the Court found that a strong exceptional case is made out by the Respondents to permit them to file affidavits/adduce additional evidence. The Court also allowed the Appellant to cross-examine and/or produce contrary evidence at the same time. In the light of the reasoning thus, the Judgment of the High Court was upheld by the Supreme Court.

0

Applicability of Section 29A of the Arbitration Act on International Commercial Arbitration post 2019 Amendment

In one of the critical steps towards making arbitration an expeditious alternative dispute resolution process, it was in 2015 that the timelines for winding up arbitration proceedings, within a stipulated time period of 12 months from the date arbitral tribunal enters upon reference, was first introduced in Indian arbitration regime vide new Section 29 A of Arbitration and Conciliation Act, 1996 (“Arbitration Act”). While the timelines were made applicable to both domestic and international arbitrations in India in 2015, its applicability was limited to domestic arbitrations alone vide an Amendment Act in 2019. The issue, whether the 2019 amendment would apply to arbitrations pending when the Amendment Act 2019 came into effect, or in other words whether the amendment is retrospective in nature, arose in several disputes and since been addressed by various High Courts including Hon’ble Delhi High Court.

One such dispute has been recently decided by the Hon’ble Supreme Court in TATA Sons Pvt Ltd (Formerly TATA Sons Ltd) v. Siva Industries and Holdings Ltd & Ors [Miscellaneous Application No 2680 of 2019 in Arbitration Case (Civil) No 38 of 2017 decided on 05.01.2023]. In this matter, a sole arbitrator was appointed by the Supreme Court under section 11(6) of the Arbitration Act since one of the respondents was a foreign party and thus, it was an international commercial arbitration in terms of Section 2(1)(f) of the Arbitration Act. The arbitrator entered upon the reference on 14 February 2018. On 21 March 2018, a preliminary case management meeting was held between the parties and the arbitrator at which the parties agreed to a six months extension (expiring on 14 August 2019), if the arbitral proceedings could not be completed within a period of twelve months commencing from the date the arbitral tribunal entered reference.

During the pendency of the arbitral proceedings, the Corporate Insolvency Resolution Process under the Insolvency and Bankruptcy Code, 2016 was initiated against the first respondent and consequently proceedings came to a suspended halt on account of moratorium. During the period of moratorium, the original period of one year and the extension of six months expired. Tata Sons, therefore, moved an application for further period of six months after the moratorium ceases to exist in the light of section 29A of the Arbitration Act as amended in 2019. CIRP came to an end on 3 June 2022. The application, therefore, sought that arbitration proceedings may be allowed to continue without any need for an extension of the term of the Ld. Sole Arbitrator or alternatively, if Hon’ble Court is of the opinion that the amended Section 29A (following the 2019 Amendment) is inapplicable to the arbitration proceedings, then allow the extension of the time limit within which arbitrator is to render an award in the arbitration proceedings between the parties by a period of 1 year.

The Court went into the analysis of Section 29A of the Arbitration Act and its evolution. When the section was introduced in 2015, it stipulated that the award shall be made within a period of twelve months from the date the arbitral tribunal enters upon the reference. Post amendment in 2019 (w.e.f. 30.08.2019), the new section 29A(1) stipulated that “The award in matters other than international commercial arbitration shall be made by the arbitral tribunal within a period of twelve months from the date of completion of pleadings under sub-section (4) of section 23: Provided that the award in the matter of international commercial arbitration may be made as expeditiously as possible and endeavor may be made to dispose of the matter within a period of twelve months from the date of completion of pleadings under sub-section (4) of section 23.”

Essentially the argument of the applicant was that as a result of the amendment of Section 29A, the period of 12 months prescribed for making an award from the date of completion of the pleadings has ceased to apply to an international commercial arbitration and the amendment being of a procedural nature, the amended provision would apply to the arbitral proceedings in the present case. The Court appreciated the mandatory nature of the provisions under Section 29A(1) prior to the amendment and their application to all arbitrations conducted under the Act, domestic or international commercial by underlining the importance of expression “shall”. The Court observed that after the amendment, the expression “in matters other than an international commercial arbitration” makes it abundantly clear that the timeline of twelve months which is stipulated in the substantive part of Section 29A(1), as amended, does not apply to international commercial arbitrations. The proviso further reaffirms that the award in the matter of an international commercial arbitration “may be made as expeditiously as possible” and that an “endeavour may be made to dispose of the matter within a period of 12 months” from the date of the completion of pleadings. Therefore while the mandate to deliver the arbitral award within the period of 12 months is mandatory for domestic arbitration, it is directory in case of international commercial arbitration.

The applicant had also argued that even if the court is of the opinion that section 29A excludes the mandate in case of international commercial arbitration, sub-section (3) and (4) were not excluded and the parties may mutually agree to extend the period by six months. In order to decide the issue, the Court went into the reasons why the report dated 30 July 2017 of the Committee chaired by Justice B N Srikrishna carries specific recommendation to the effect that international commercial arbitrations may be left outside the purview of the timelines provided in Section 29A. The Committee indicated that generally the  international arbitration institutions, with their own machinery for case management, have in place the timelines for conducting international arbitrations and that they did not require the monitoring of timelines by the intervention of the court. The Committee further recorded that in other jurisdictions, timelines for arbitral proceedings are usually agreed by the parties themselves in accordance with the nature and complexity of the dispute.

On aspect of applicability of the 2019 amendments to Section 29A to the present case, the Court referred to section 26 of the 2015 Amendment Act which clarified that “[n]othing contained in this Act shall apply to the arbitral proceedings commenced, in accordance with the provisions of Section 21 of the principal Act, before the commencement of this Act unless the parties otherwise agree but this Act shall apply in relation to arbitral proceedings commenced on or after the date of commencement of this Act.”

The Court observed that no provision equivalent to section 26 of the 2015 Amendment Act with regard to the prospective application of the amendments was chalked under the Amendment Act of 2019. Further, the removal of the mandatory time limit for making an arbitral award in the case of an international commercial arbitration does not confer any rights or liabilities on any party and is remedial in nature (unlike original Section 29A which despite being procedural in nature created new obligations in respect of a proceeding which had already commenced since it laid down a strict timeline for rendering an arbitral award for the first time in the framework of the Arbitration Act [Board of Control for Cricket in India v. Kochi Cricket Pvt. Ltd[1]]). Accordingly, the Court held that Section 29A should be applicable to all pending arbitral proceedings as on the effective date i.e., 30 August 2019. The Court agreed with the decision of Hon’ble Delhi High Court in the matter of ONGC Petro Additions Ltd. vs Ferns Construction Co. Inc.[OMP (Misc) (Comm) 256/2019] wherein it was held that there is no strict time line prescribed to the proceedings which are in nature of international commercial arbitration as defined under the Act, seated in India. The Court, accordingly, held that the sole arbitrator in the present case would be acting within his domain and jurisdiction to decide upon any further extension of time beyond what is originally stipulated in the case management meeting.

It is therefore, made clear beyond any doubt that the timelines stipulated under Section 29A of the Arbitration Act for concluding arbitration proceedings are not only inapplicable in case of international commercial arbitrations, the amendment in 2019 being procedural in nature is retrospective and shall be applicable to all the proceedings pending at the time the amendment came into effect.


[1] (2018) 6 SCC 287

0

Right to File Affidavits/Additional Evidence in the Proceedings under Section 34 of the Arbitration Act

It has been well established by catena of judgments that proceedings under Section 34 of the Arbitration and Conciliation Act, 1996 (“Arbitration Act“) are summary in nature and therefore, the scope of enquiry in any proceedings under Section 34 of the Act has been restricted to consider the grounds exhaustively mentioned in Section 34(2) or Section 13(5) or Section 16(6) in order to determine whether to set aside an award that has been challenged under section 34 of the Arbitration Act. The thumb rule is that an application for setting aside an arbitral award would not ordinarily require anything beyond the record that was before the Arbitral Tribunal.

In the matter of Fiza Developers and Inter-Trade Private Limited v. AMCI (India) Private Limited and Anr[1] the Court had held that framing of issues is not required as the proceedings are summary in nature. However, at the same time the Court indicated that according to section 34(2) of the Arbitration Act, an opportunity to the aggrieved party has to be afforded to prove existence of any of the grounds and allowed the applicant in the case to file affidavits of the applicant’s witnesses as “proof” and granted the respondent-defendant an opportunity to place their evidence by affidavit. The Court further went on to add that “Where the case so warrants, the court permits cross-examination of the persons swearing to the affidavit”.  

In the matter of Emkay Global Financial Services Limited v. Girdhar Sondhi[2] it was clarified thatsince after 2015 amendments to the Arbitration Act, the proceedings under section 34 have become time bound, the thumb rule of summary proceeding shall be followed and only if there were matters not contained in the record before the arbitrator, and would be relevant for determining issues arising under Section 34(2)(a), only then they may be brought to the notice of the Court by way of affidavits filed by both parties. The Court further added that cross-examination of persons swearing to the affidavits should not be allowed unless absolutely necessary.

Since, clearly an exception has been carved out to the thumb rule, howsoever narrow, the question is how and when this exception be applied by the courts. When is it ‘absolutely necessary’ to cross examine? In a subsequent matter[3], the Apex Court further clarified the position by holding that if there is any exceptional circumstance wherein parties are required to adduce evidence in the form of an affidavit, the party must indicate on what point the party intends to adduce evidence along with disclosing specific documents or evidence that would be required to be produced. There must be specific averments in the affidavit as to the necessity and relevance of the additional evidence sought to be adduced which would be beyond the record that was before the arbitrator.

Recently, on a strong exceptional basis, the Apex Court in the matter of M/s Alpine Housing Development Corporation Pvt. Ltd. v. Ashok S. Dhariwal and Others[4] allowed a party to file affidavits/additional evidence in the proceedings under section 34 of the Arbitration Act and further permitted second party to cross-examine and/or produce contrary evidence. In this case, the award passed by the arbitrator was ex-parte. The respondent assailed the award under section 34 of the Arbitration Act along with the application to adduce additional evidence. The application was declined by the Court while relying on Section 34(2)(a) of the Act, as amended in the year 2019, by which expression “furnish proof” in section 34(2)(a) came to be substituted with the expression “establish on the basis of record of arbitral tribunal”. The Court explained in the following words: “the said amendment intended to limit the scope of judicial review under Section 34 of the Act only in exceptional circumstances enumerated under Section 34(2)(a) of the Act on the basis of the record available and even if the grounds urged relate to section 34(2)(b) of the Act, the applicants cannot have a right to produce additional evidence”. The order of the Court was challenged by way of writ petition before the High Court which allowed the petition and permitted the respondent to adduce the evidence while relying on judgment in Fiza Developers.

The said judgment by the Hon’ble High Court was challenged before the Hon’ble Supreme Court. The Court foremost observed that arbitration proceedings commenced and even the award was declared by the arbitral tribunal in the year 1998, i.e., prior to section 34(2)(a) came to be amended and therefore, pre-amendment of section 34(2)(a) shall be applicable according to which an arbitral award could be set aside by the Court if the party making an application “furnishes proof” and the grounds set out in section 34(2)(a) and section 34(2)(b) are satisfied.

The Court, therefore, applied the ratio in the judgments in Fiza Developers, Emkay Global and Canara Nidhi, and held that “if there are matters not containing such records and the relevant determination to the issues arising under section 34(2)(a), they may be brought to the notice of the Court by way of affidavits filed by both the parties”. The Court observed that whereas the arbitral tribunal in the matter had passed the decree for specific performance of the contract/agreement subject to the amalgamation of the plots, the respondents, by way of application, had sought to place on record the communication from the appropriate authority by which the application for amalgamation of the plots was rejected. The case of the respondents was thus, in view of the refusal of the permission by the appropriate authority to amalgamate the plots, the case fell under section 34(2)(b), namely, that the dispute was not capable of settlement under the law for the time being in force and that the arbitral award was in conflict with the Public Policy of India, namely, against the relevant land laws. Since the event of refusal to amalgamate the plots was subsequent to the passing of the award, the same was not forming part of the record of the arbitral tribunal. Further, the award of the arbitral tribunal being an exparte award, no evidence was before the arbitral tribunal on behalf of the respondents.

According to the Court, therefore, the affidavit thus disclosed specific document and the evidence required to be produced, thus establishing a strong exceptional case to permit the respondents to file affidavits/adduce additional evidence. However, despite the Courts observation that “the cross-examination of the persons swearing in to the affidavits should not be allowed unless absolutely necessary as the truth will emerge on the reading of the affidavits filed by both the parties,” no separate reasoning was provided by the Court for allowing cross-examination in the matter. The Court plainly added that, “at the same time, the appellant also can be permitted to cross-examine and/or produce contrary evidence.”

It is pertinent to note that as it appears, the permission to adduce additional evidence has been granted because the pre-amendment position of law has been applied. This was because not only were the proceedings commenced before the amendments, the award was also delivered prior to the amendments. After the amendment in 2019, the section does away with the requirement of furnishing proof under Section 34(2)(a) of the Arbitration Act. The phrase “party making the application furnishes proof” has been substituted with the words “establishes on the basis of the Arbitral Tribunal’s record that.” Further, the proceedings under section 34 before the Court has been made time bound.


[1] (2009 ) 17 SCC 796

[2] (2018) 9 SCC 49

[3] The judgment in Canara Nidhi Limited vs. M. Shashikala Civil Appeal Nos. 7544-7545 of 2019 further affirms the position.

[4] [CIVIL APPEAL NO. 73 OF 2023 decided on  19.01.2023]

0

Duty of the Courts to Examine the Arbitrability of Disputes at the Reference Stage

In a recent case of M/s. Emaar India Ltd. v. Tarun Aggarwal Projects LLP & Anr [CIVIL APPEAL NO.  6774 OF 2022], once again question that emerged  for the consideration of Hon’ble Supreme Court was whether the High Court was justified  in allowing  the   application   under  Section   11(5)   &  (6)  of the Arbitration and Conciliation Act, 1996 for appointing the arbitrators without considering the aspect of arbitrability of dispute as per the relevant clauses under the Agreement.  As per the Agreement executed between the parties, if any conflict or difference arose between the parties or in case either party refuses or neglects to perform its part of the obligations under Agreement,  then such issues were not arbitrable but the other party had right to get the agreement specifically enforced through the appropriate court of law. Therefore, the question whether the dispute is arbitrable or not, was to be considered by the Court or by the arbitral tribunal in the light of the very terms of the said agreement.

The Court while analysing the issue went into underling the relevance of contract and observed that the reliefs to the parties shall not travel beyond the terms of the contract executed between the parties. It is because a contract is a transaction between two parties and has been entered into with open eyes and by understanding the nature of contract and that such contract has to   be interpreted giving literal meanings unless there is some ambiguity therein. The Court further referred to the judgment in Harsha  Construction  Vs.  Union  of  India and Ors.  (2014) 9 SCC 246 and observed that a contract with regard to arbitration has to be an expressed one. It must be in writing as per the legislation. In Harsha  Construction case it was clearly held that it was not open to the Arbitrator to arbitrate upon the disputes which had   been expressly  “excepted” and thus non-arbitrable. An award, therefore, so far as it related to disputes   regarding   non¬arbitrable   disputes  was bad in law  and liable to be quashed.

The Court further referred to the judgment in Vidya Drolia and Ors. Vs. Durga Trading Corporation (2021) 2 SCC 1 to elaborate on the aspect of arbitrability and its determination at the stage of application under section 11(6) of the Arbitration and Conciliation Act, 1996. The Court observed that the issue of non-arbitrability of a dispute is basic for arbitration as it relates to the very jurisdiction of the Arbitral Tribunal. As per Vidya Drolia and a catena of judgments decided earlier, the question of arbitrability, specially relating   to   the   inquiry whether   the   dispute   was   governed   by   the   arbitration clause, can be examined by the Courts at the reference stage itself. Further, Court can examine the validity   of   an arbitration   agreement, the authority which is covered by the expression, “existence of arbitration agreement” in Section 11 of the Arbitration   Act. Court shall not refer the matter for arbitration and as a demurrer interfere under section 8 and 11 when  it is manifestly and ex facie certain   that   the   arbitration   agreement   is   non-¬existent, invalid or the disputes are non-arbitrable and also when the matter is demonstrably “non-arbitrable   and   to   cut   off   the deadwood.”  The judicial scrutiny may however vary with the nature and   facet   of   non-arbitrability. If, however, the contentions relating to non–arbitrability are plainly arguable, the court by default shall refer the matter for arbitration. Applying the law laid down by this Court in the aforesaid decisions, the Court in the present matter held that the dispute is not arbitrable since the claims have been excepted by the clear term in the Agreement.

0

The Arbitral Tribunal is Cast With Duty to Give Reasons While Exercising Its Discretion Under Section 31(7) of the Arbitration and Conciliation Act

Hon’ble Supreme Court in a recent judgment[1] held that when a discretion is vested in the Arbitral Tribunal under Section 31(7) of the Arbitration and Conciliation Act, 1996 to determine the rate of interest, whether the interest is payable on whole or any part of the money  and whether it is to be awarded to the whole or any part of the  period stipulated, the Tribunal has the duty to apply its mind and give reasons as to how it deems a certain interest rate as reasonable and to decide why the interest is payable on whole or any part of the money and also as to why it is to be awarded to the whole or any part of the  period between the date on which the cause of action arose and the date on which the award is made. While exercising its jurisdiction under Article 142 of the Constitution of India, The Hon’ble Court reduced the rate of interest from 18% to 9% and further reduced the period by 20 odd years on account of the lapse of the Claimant-Respondent in taking timely action.

The Respondent was awarded the contract for construction of missing link of 3 kms stretch on NH­6 on 16th December, 1971 to be completed within one year. The contract amount was Rs.4,59,330/­.   However the work could be completed by 30th August 1977. The Respondent was already paid an amount of Rs.3,36,465/­ by then. The Respondent issued a notice to the Appellant regarding his claim only on 25th July 1989 followed by the Respondent filing his claim of Rs.1,45,28,198/­ and interest @ 19.5% from 1st April 1976 to 15th March 2002.  The learned   Arbitrator,   vide   award   dated   24th August   2004, awarded a sum of Rs.9,20,650/­ and an interest  pendent lite with effect from 1st April 1976 to the date of the award at the rate of 18% per annum which came to Rs. 46,90,000/­. The learned Arbitrator further directed the future interest to be paid at the rate of 18% per annum on the total of the aforesaid two amounts till actual payment.

The Award was challenged on various grounds including on the ground that the interest   amount   of   Rs.46,90,000/­   is almost   five   times   that   of   the   main   award   amount   of Rs.9,20,650/­. The Appellant relied on the judgments in Rajendra   Construction   Co.   v.   Maharashtra Housing   &   Area   Development   Authority   and   Others [(2005) 6 SCC 678], Krishna   Bhagya   Jala   Nigam   Ltd.   v.   G.   Harischandra Reddy and Another [(2007) 2 SCC 720] and Mcdermott International Inc. v. Burn   Standard   Co.   Ltd.   and   Others [(2006) 11 SCC 181].

The Court examined the issue in the light of the discretion given to an Arbitral Tribunal under Section 31(7) of the Arbitration and Conciliation Act, 1996 (“1996 Act”) to determine the rate of interest, whether interest would be applicable on the whole or any part of the money awarded, and whether it shall be applicable for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made. The Court arrived at the decision that such discretion when vested in the Arbitral Tribunal, it has a duty to exercise the discretion while applying its mind to the facts and circumstances of the case and give reasons for arriving at a certain interest rate, the sum of which it shall be applicable, and period for which it shall apply.

The Court observed that the Arbitral Tribunal in the matter did not do any such exercise of reasoning and further failed to exclude the period of more than 20 years during which it was the Respondent-Claimant who did not raise its claim and further did not take any action after decree was passed in 1990 and then after passing of 1996 Act until 2001 when the Respondent-Claimant finally filed an application under section 11 of the 1996 Act. The Court in this regard held that a party cannot be permitted to derive benefits from its own lapses. With regard to the determination of the rate of interest, the Court made reference to various judgments including the observation made by the Court in Mcdermott International Inc. wherein it was held that given the long lapse of time, it will be in furtherance of justice to reduce the rate of interest while exercising the jurisdiction under Article 142 of the Constitution of India. The Court, accordingly found that the present case was also a fit case wherein this Court needed to exercise its powers under Article 142 of the Constitution of India to reduce the rate of interest. While taking into consideration the conduct of the Respondent in delaying the proceedings at every stage which led to a long pendency of the dispute, the Court concluded that, though it will not be in the interest of justice to interfere with the principal award, it would be a fit case wherein the interest at all the three stages, that is pre­reference period, pendente lite and post­award period, requires to be reduced. The Court, therefore, was pleased to reduce the rate of interest to 9% from 18%


[1] Executive Engineer (R and B) and Ors. v. Gokul Chandra Kanungo (Dead) Thr. His Lrs. [CIVIL APPEAL NO. 8990 OF 2017 decide on 30.09.2022]

1 2 3 4 5

You cannot copy content of this page

Left Menu Icon

DISCLAIMER & CONFIRMATION

The Bar Council of India does not permit advertisement or solicitation by advocates in any form or manner.

By clicking “Proceed” button below and accessing this website (www.nautiliyaalegal.com), the user fully accepts that he/she is seeking information of his/her own accord and volition and that no form of solicitation has taken place by the firm or its members.

The information provided under this website is solely available at your request for information purposes only. It should not be interpreted as soliciting or advertisement. The firm is not liable for any consequence of any action taken by the user relying on material / information provided under this website. In cases where the user has any legal issues, he/she in all cases must seek independent legal advice.